Direction (Qs.1 to 5): Study the following line graph carefully and answer the questions given below.
Line graph shows, the number of days six people took to complete the work individually.
Question No : 1
If A and B started doing the work. After 3 days they both left, and M joined the work. Now the remaining work was completed by M in 10 days. In how many days can M complete the whole work?
(1) 42
(2) 10
(3) 40
(4) 28
(5) 18.18
Question No : 2
What will be the ratio of wages if all the six people work together?
(1) 42 : 21 : 84 : 140 : 60 : 105
(2) 10 : 20 : 5 : 3 : 7 : 4
(3) 40 : 20 : 82 : 140 : 60 : 105
(4) 42 : 21 : 82 : 140 : 601 : 109
(5) 10 : 20 : 5 : 30 : 70 : 4
Question No : 3
If B and E started doing the work. After 1 day they both left, and N joined the work. Now the remaining work was completed by N in 5 days. In how many days can N alone complete the whole work?
(1) 6.19
(2) 7
(3) 5
(4) 4.2
(5) 1.8
Question No : 4
If the efficiency of all the worker is improved by 33.33%, then in how many days the work will be completed?
(1) 0.69 days
(2) 1 days
(3) 2 days
(4) 1.33 days
(5) 1.8 days
Question No : 5
If all the people divide the work equally. In how many days will the work be completed this way?
(1) 42
(2) 10
(3) 40
(4) 18
(5) 8.17